Week 23
Cutler Construction reported at this week’s construction meeting that they were one week away from being completely closed in. The final exterior masonry is about complete and once this is done the pre-engineered building shell crew will return followed by the glass company to install glass in each of the many windows. Rough-in work by plumbers, electricians and HVAC contractors continues with a rough inspection due for electrical and plumbing in two weeks. Cutler requested that we ask the gas company to install the gas line on Hale Street as quickly as possible since once enclosed the building will need heat and once interior finishes begin both heat and humidity control will be critical. I was also given a report from Cutler which showed that 93.6% of all waste created by this project was recycled and removed from the waste stream. The project continues to be on track for a late May opening.
Dave Seiter